Grogan Excavation was at Shrine Wednesday, January 12th. They graded the new utility line trench, took down dead trees and burned the big pile, placed some gravel and dirt around the slab, and installed drain pipe on south side as well as graded drainage.
Update: Dec. 8 2021
Today I received these photos from Doug Zimpfer that the gentleman is pouring the cement. So we have more progress. I believe that this is the final step until springtime. -Rosemary Speaker